CV0-004 Domain 3: Cloud Deployment

A regulated workload requires the organization to blue/green or canary releases. Which solution is BEST?

Multiple choice — select one answer

Answer choices

  1. a. Gradual traffic shift
  2. b. Replace servers instead of patching in place
  3. c. Infrastructure as code templates
  4. d. Pipeline with tests and approvals

Architectural breakdown & explanation

Progressive delivery limits blast radius.

Correct answer(s): a. Gradual traffic shift

Exam domain: Domain 3: Cloud Deployment (25% weight on the official guide).

Official documentation & study links

Practice this certification

This page is one question from the CompTIA Cloud+ bank. Run a full timed practice exam with domain-weighted random questions in your browser.