An audit found gaps: the organization must define requirements before build. Which option addresses this?
Multiple choice — select one answer
Answer choices
Architectural breakdown & explanation
Baselines control scope creep.
Correct answer(s): a. Approved requirements baseline
Exam domain: Domain 2: Project Life Cycle Phases (30% weight on the official guide).