PK0-005 Domain 2: Project Life Cycle Phases

An audit found gaps: the organization must define requirements before build. Which option addresses this?

Multiple choice — select one answer

Answer choices

  1. a. Approved requirements baseline
  2. b. Risk register with owners and responses
  3. c. No sign-off
  4. d. Work breakdown structure decomposition

Architectural breakdown & explanation

Baselines control scope creep.

Correct answer(s): a. Approved requirements baseline

Exam domain: Domain 2: Project Life Cycle Phases (30% weight on the official guide).

Official documentation & study links