PK0-005 Domain 2: Project Life Cycle Phases

A company needs to manage project risks. Which option meets the requirement with the LEAST implementation effort?

Multiple choice — select one answer

Answer choices

  1. a. Work breakdown structure decomposition
  2. b. No mitigation (not recommended for production workloads)
  3. c. Approved requirements baseline
  4. d. Risk register with owners and responses

Architectural breakdown & explanation

Risk management reduces surprises.

Correct answer(s): d. Risk register with owners and responses

Exam domain: Domain 2: Project Life Cycle Phases (30% weight on the official guide).

Official documentation & study links

Practice this certification

This page is one question from the CompTIA Project+ bank. Run a full timed practice exam with domain-weighted random questions in your browser.