PK0-005 Domain 2: Project Life Cycle Phases

For compliance, the team must define requirements before build.

Multiple choice — select one answer

Answer choices

  1. a. Work breakdown structure decomposition
  2. b. Approved requirements baseline
  3. c. Risk register with owners and responses
  4. d. No sign-off

Architectural breakdown & explanation

Baselines control scope creep.

Correct answer(s): b. Approved requirements baseline

Exam domain: Domain 2: Project Life Cycle Phases (30% weight on the official guide).