For compliance, the team must define requirements before build.
Multiple choice — select one answer
Answer choices
Architectural breakdown & explanation
Baselines control scope creep.
Correct answer(s): b. Approved requirements baseline
Exam domain: Domain 2: Project Life Cycle Phases (30% weight on the official guide).
Official documentation & study links
Practice this certification
This page is one question from the CompTIA Project+ bank. Run a full timed practice exam with domain-weighted random questions in your browser.