PK0-005 Domain 2: Project Life Cycle Phases

For compliance, the team must track work with WBS.

Multiple choice — select one answer

Answer choices

  1. a. Approved requirements baseline
  2. b. Work breakdown structure decomposition
  3. c. Ignore dependencies (not recommended for production workloads)
  4. d. Risk register with owners and responses

Architectural breakdown & explanation

WBS clarifies deliverables.

Correct answer(s): b. Work breakdown structure decomposition

Exam domain: Domain 2: Project Life Cycle Phases (30% weight on the official guide).

Official documentation & study links

Practice this certification

This page is one question from the CompTIA Project+ bank. Run a full timed practice exam with domain-weighted random questions in your browser.