PK0-005 Domain 2: Project Life Cycle Phases

What should you do FIRST to manage project risks?

Multiple choice — select one answer

Answer choices

  1. a. No mitigation (not recommended for production workloads)
  2. b. Approved requirements baseline
  3. c. Work breakdown structure decomposition
  4. d. Risk register with owners and responses

Architectural breakdown & explanation

Risk management reduces surprises.

Correct answer(s): d. Risk register with owners and responses

Exam domain: Domain 2: Project Life Cycle Phases (30% weight on the official guide).