PK0-005 Domain 2: Project Life Cycle Phases

A technician must define requirements before build. What is the best choice?

Multiple choice — select one answer

Answer choices

  1. a. Work breakdown structure decomposition
  2. b. Risk register with owners and responses
  3. c. Approved requirements baseline
  4. d. No sign-off

Architectural breakdown & explanation

Baselines control scope creep.

Correct answer(s): c. Approved requirements baseline

Exam domain: Domain 2: Project Life Cycle Phases (30% weight on the official guide).