PK0-005 Domain 2: Project Life Cycle Phases

During troubleshooting, you must define requirements before build.

Multiple choice — select one answer

Answer choices

  1. a. No sign-off
  2. b. Work breakdown structure decomposition
  3. c. Risk register with owners and responses
  4. d. Approved requirements baseline

Architectural breakdown & explanation

Baselines control scope creep.

Correct answer(s): d. Approved requirements baseline

Exam domain: Domain 2: Project Life Cycle Phases (30% weight on the official guide).